Alternative Dispute Resolution
Afcons Infrastructure Ltd. v. Cherian Varkey Construction Co. (P) Ltd.
(2010) 8 SCC 24
- Citation
- (2010) 8 SCC 24
- Court
- Supreme Court of India
- Date
- 26 July 2010
- Bench
- R.V. Raveendran and J.M. Panchal, JJ.
Facts
- Cochin Port Trust awarded infrastructure work involving bridges and roads to Afcons Infrastructure.
- Afcons subcontracted part of that work to Cherian Varkey Construction Co.
- The subcontract did not contain an arbitration clause.
- Cherian Varkey later filed a civil suit seeking recovery of approximately ₹2.10 crore.
- During the suit, it applied under Section 89 CPC and requested that the dispute be referred to arbitration.
- Afcons expressly objected to:
- arbitration; and
- the other ADR methods proposed at that stage.
- Despite this objection, the trial court held that a construction dispute was suitable for arbitration and referred it accordingly.
- The trial court framed sixteen issues for the arbitrator.
- The Kerala High Court upheld the order.
- It reasoned that Section 89 permitted courts to refer unwilling parties to arbitration even without a pre-existing arbitration agreement.
- Afcons appealed to the Supreme Court.
Issue
- Whether Section 89 permits a civil court to compel parties to arbitrate without their consent.
- What procedure courts should follow when applying Section 89 and Order X Rule 1A.
- Which categories of disputes are ordinarily suitable or unsuitable for ADR.
Rule
- Arbitration is an adjudicatory process based on consent.
- A court cannot refer parties to arbitration unless:
- a valid arbitration agreement already exists; or
- all parties subsequently agree in writing to arbitration.
- Conciliation similarly depends upon consent.
- Courts must nevertheless conduct a meaningful Section 89 examination after pleadings are complete and before trial.
- For non-adjudicatory processes such as mediation, Lok Adalat and judicial settlement, the court has wider power to make a suitable referral.
- The judge need not formulate detailed settlement terms before reference.
- It is sufficient to briefly identify the nature of the dispute and choose the appropriate ADR process.
Application
- The Supreme Court first addressed drafting defects in Section 89.
- The statutory descriptions of “mediation” and “judicial settlement” had effectively been interchanged.
- The section also unrealistically appeared to require a judge to formulate and reformulate settlement terms before sending parties to ADR.
- The Court corrected these anomalies through purposive interpretation.
- The trial court should not attempt to negotiate the entire settlement itself.
- It should:
- examine the pleadings;
- identify the dispute;
- consider whether settlement is reasonably possible;
- hear the parties on the appropriate process; and
- make a suitable reference.
- The Court then distinguished arbitration from mediation.
- Arbitration replaces the civil court with a private adjudicator who gives a binding award.
- Such transfer of adjudicatory authority cannot occur without party consent.
- In the present case:
- the subcontract contained no arbitration clause;
- Afcons had expressly refused arbitration; and
- no later written arbitration agreement was created.
- The trial court therefore had no authority to impose arbitration merely because it considered arbitration efficient.
- The Court also offered guidance on suitability.
- Cases ordinarily suitable for ADR include:
- commercial and contractual claims;
- money disputes;
- family disputes;
- consumer matters;
- tort claims; and
- disputes involving continuing relationships.
- Cases ordinarily unsuitable include:
- representative suits;
- election disputes;
- probate matters;
- serious allegations of fraud or coercion;
- cases affecting minors or persons under disability;
- certain public-law claims; and
- criminal prosecutions.
- These categories were guides rather than inflexible rules.
- The Court emphasised that considering ADR is mandatory, but achieving settlement is not.
- A court must make an honest assessment and record why reference is or is not appropriate.
Conclusion
- The Supreme Court set aside the compulsory reference to arbitration.
- It held that arbitration under Section 89 requires the consent of all parties.
- The matter was returned to the trial court to consider whether another suitable ADR process could be used.
- The Court laid down a comprehensive practical roadmap for Section 89 referrals.
- Use this case for: courts must consider ADR, but they cannot compel parties to arbitrate without an arbitration agreement or subsequent consent.