Alternative Dispute Resolution
Delhi Metro Rail Corporation Ltd. v. Delhi Airport Metro Express Pvt. Ltd.
(2024) 5 SCC 197; 2024 INSC 292
- Citation
- (2024) 5 SCC 197; 2024 INSC 292
- Court
- Supreme Court of India
- Date
- 10 April 2024
- Bench
- D.Y. Chandrachud, C.J.; B.R. Gavai and Surya Kant, JJ.
Facts
- DMRC granted DAMEPL a concession to design, operate and maintain the Delhi Airport Metro Express Line.
- Serious defects appeared in the civil structure, including bearings and other components.
- DAMEPL issued a cure notice and later terminated the concession agreement.
- DMRC maintained that:
- the defects were repairable;
- substantial corrective work had been completed;
- and termination was invalid.
- The tribunal upheld DAMEPL’s termination and awarded a large termination payment with interest.
- A Single Judge upheld the award.
- A Division Bench partly set it aside.
- In 2021, the Supreme Court restored the award.
- DMRC’s review petitions failed.
- It then filed curative petitions, contending that the earlier Supreme Court decision had resulted in a fundamental miscarriage of justice.
- In 2024, the Supreme Court reconsidered the case through its extraordinary curative jurisdiction.
Issue
- Whether the award suffered from patent illegality.
- Whether the tribunal ignored vital contractual and technical evidence.
- Whether the exceptional curative jurisdiction could be used in an arbitration dispute.
- Whether the Court was impermissibly reassessing the merits.
Rule
- Curative jurisdiction is much narrower than:
- Section 34;
- Section 37;
- appeal;
- or ordinary review.
- It may be exercised only to prevent a grave miscarriage of justice and preserve the integrity of the judicial process.
- An award may be patently illegal where the tribunal:
- ignores vital evidence;
- disregards an express contractual requirement;
- adopts a conclusion not reasonably possible;
- or fails to address the contractual cure mechanism.
- Nevertheless, curative jurisdiction cannot become a routine third or fourth level of arbitral review.
Application
- The Court examined whether the tribunal had properly addressed the contractual standard for termination.
- The agreement required assessment of:
- the nature of defects;
- whether they were cured within the specified period;
- the safety certification process;
- and the effect of corrective measures.
- The Court concluded that the tribunal had:
- ignored material evidence showing substantial rectification;
- failed to apply the contractual cure requirements;
- treated technical concerns as automatically justifying termination;
- and reached conclusions inconsistent with the record.
- The 2021 Supreme Court judgment had restored the award without adequately identifying these defects.
- According to the curative Bench, that restoration placed an enormous liability upon a public utility on the basis of a fundamentally flawed award.
- It therefore found a rare miscarriage of justice sufficient to reopen the final Supreme Court decision.
- The Court stressed that its intervention was not based merely on another possible interpretation.
- It considered the award to be one that no reasonable tribunal could have made after applying the contract and vital evidence.
- The decision has attracted concern because curative intervention may appear inconsistent with arbitral finality.
- The Court itself therefore emphasised that:
- the remedy is extraordinary;
- public-sector involvement or the size of an award is not enough;
- and ordinary disagreements must end under Sections 34 and 37.
- The judgment should not be treated as creating a routine curative appeal against awards.
Conclusion
- The Supreme Court allowed DMRC’s curative petitions.
- It set aside the earlier Supreme Court judgment and the arbitral award.
- It held that the tribunal’s disregard of vital evidence and the cure provisions produced patent illegality and a grave miscarriage of justice.
- Use this case for: the exceptionally rare curative correction of an award-related Supreme Court judgment.