Alternative Dispute Resolution
M.R. Engineers & Contractors Pvt. Ltd. v. Som Datt Builders Ltd.
(2009) 7 SCC 696
- Citation
- (2009) 7 SCC 696
- Court
- Supreme Court of India
- Date
- 7 July 2009
- Bench
- R.V. Raveendran and J.M. Panchal, JJ.
Facts
- Som Datt Builders Ltd. entered into a main construction contract with the Kerala Public Works Department.
- The main contract contained a detailed arbitration clause governing disputes between:
- the government employer; and
- Som Datt as the principal contractor.
- Som Datt later issued a work order or subcontract to M.R. Engineers & Contractors Pvt. Ltd.
- The subcontract stated that the work would be carried out according to the terms and conditions applicable to the main contract.
- The subcontract did not reproduce the main contract’s arbitration clause.
- Nor did it expressly state that the arbitration clause in the main contract was incorporated.
- Disputes arose concerning:
- extra work;
- payment; and
- performance of the subcontract.
- M.R. Engineers sought appointment of an arbitrator under Section 11.
- It argued that the general reference to the main contract incorporated all its terms, including arbitration.
- Som Datt disputed the existence of an arbitration agreement between the subcontracting parties.
Issue
- Whether a general reference to the terms of a main contract incorporates its arbitration clause into a subcontract.
- What degree of reference is required under Section 7(5).
- Whether the arbitration clause in the main contract could operate consistently between the principal contractor and subcontractor.
Rule
- Section 7(5) permits incorporation of an arbitration clause contained in another document.
- Incorporation requires a reference showing an intention to make that arbitration clause part of the contract.
- A distinction exists between:
- reference to a standard form containing an arbitration clause; and
- reference to a separate contract between different parties.
- A general reference may incorporate a standard form because the entire standard conditions are commonly adopted as a package.
- Where the referenced document is a separate contract, a specific reference to its arbitration clause is ordinarily required.
- The incorporated clause must also be capable of operating within the later contract without inconsistency or substantial modification.
Application
- The Supreme Court examined the wording of the subcontract.
- It required M.R. Engineers to perform the construction work according to specifications, technical requirements and other operational conditions derived from the main contract.
- This showed an intention to import provisions relevant to execution of the work.
- It did not necessarily show an intention to import the dispute-resolution mechanism.
- The main contract’s arbitration clause had been drafted specifically for disputes between the Kerala Government and Som Datt.
- It referred to:
- officials of the government department;
- appointment powers held by persons who were not parties to the subcontract;
- procedures connected with the main employer; and
- rights and duties particular to the principal contract.
- The clause could not operate automatically between Som Datt and M.R. Engineers without major adaptation.
- This supported the conclusion that it had not been consciously adopted.
- The Court emphasised that an arbitration agreement removes disputes from ordinary courts.
- Such consent should not be inferred from vague language dealing primarily with performance obligations.
- If Som Datt and M.R. Engineers intended to arbitrate, the work order could easily have stated:
- that the main contract’s arbitration clause applied; or
- that disputes under the subcontract would be referred to arbitration.
- It did neither.
- The Court distinguished general incorporation of standard institutional conditions.
- Where a contract states that it is subject to a recognised standard form, the parties may reasonably be taken to have adopted the whole form, including arbitration.
- Here, however, the main contract was a distinct agreement between different parties.
- The general reference was therefore insufficient.
- No independent exchange of correspondence or later conduct established an agreement to arbitrate.
- The Section 11 request consequently lacked the foundational requirement of an existing arbitration agreement.
Conclusion
- The Supreme Court held that the arbitration clause in the main contract was not incorporated into the subcontract.
- The general reference to the main contract’s terms concerned execution of work and did not amount to conscious adoption of arbitration.
- The request for appointment of an arbitrator was rejected.
- Use this case for: a general reference to another independent contract ordinarily does not incorporate its arbitration clause without a specific and workable adoption.