Alternative Dispute Resolution
McDermott International Inc. v. Burn Standard Co. Ltd.
(2006) 11 SCC 181
- Citation
- (2006) 11 SCC 181
- Court
- Supreme Court of India
- Date
- 12 May 2006
- Bench
- S.B. Sinha and P.P. Naolekar, JJ.
Facts
- Burn Standard engaged McDermott International for offshore construction work connected with ONGC projects.
- The contract covered fabrication, transportation, installation and commissioning of offshore facilities.
- Serious disputes arose concerning:
- delay;
- additional work;
- change orders;
- prolongation costs;
- payment;
- interest; and
- responsibility for disruption.
- Arbitration took place and substantial awards were made in favour of McDermott.
- Burn Standard challenged the awards under Section 34.
- It argued that:
- the tribunal used inappropriate methods to calculate delay damages;
- particular claims were barred by the contract;
- the evidence was insufficient;
- and the court should correct or reduce the awarded amounts.
- The dispute reached the Supreme Court.
Issue
- What is the role of a Section 34 court?
- Whether a court may correct or modify an erroneous award.
- Whether the tribunal’s choice of a damages-calculation method may be reconsidered.
- When contractual interpretation becomes jurisdictional excess.
Rule
- Under Section 34, the court exercises supervisory rather than appellate jurisdiction.
- The court may:
- set aside an award on a statutory ground; or
- adjourn proceedings under Section 34(4) to allow the tribunal to eliminate a curable defect.
- It cannot ordinarily:
- correct factual findings;
- rewrite the reasoning;
- calculate a different amount;
- or substitute its own award.
- The tribunal may select a recognised method for assessing damages where:
- exact calculation is difficult;
- sufficient evidence exists;
- and the method is rationally connected with the loss.
- Contract interpretation is primarily for the arbitrator.
Application
- The tribunal had considered voluminous technical and financial material concerning the offshore project.
- It used accepted industry methodologies to estimate prolongation and delay costs.
- Burn Standard argued that a different formula should have been applied.
- The Supreme Court held that choosing among recognised methods was an arbitral function.
- A court cannot reject an award merely because:
- another calculation might be more accurate;
- the evidence could be assessed differently;
- or the result is substantial.
- The tribunal had given reasons and linked the claims with:
- additional work;
- employer-caused delay;
- project records;
- and the contract.
- The Court therefore refused a general merits reconsideration.
- It also gave an influential explanation of Section 34:
- the court does not sit in appeal;
- judicial intervention is limited;
- and an award ordinarily survives unless a statutory defect is proved.
- The judgment stated categorically that courts may quash but cannot modify an award.
- That statement governed Indian law for many years and was reaffirmed in M. Hakeem.
- It has now been qualified by Gayatri Balasamy, which recognises narrow modification powers in specific circumstances.
- However, McDermott’s core prohibition remains:
- a court cannot reassess the merits and construct a new award of its own.
- The Court also adjusted aspects of post-award interest in accordance with the statutory framework and the particular contractual position, while preserving the substantive arbitral determinations.
- The decision remains a foundational explanation of minimal judicial intervention.
Conclusion
- The Supreme Court substantially upheld the arbitral findings and refused to recalculate the merits.
- It held that Section 34 courts supervise legality but do not correct or replace arbitral reasoning.
- Its absolute statement against modification is now qualified only by the narrow categories recognised in Gayatri Balasamy.
- Use this case for: the supervisory, non-appellate character of Section 34 and the traditional rule against judicial rewriting of awards.