Alternative Dispute Resolution
Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India
(2019) 15 SCC 131
- Citation
- (2019) 15 SCC 131
- Court
- Supreme Court of India
- Date
- 8 May 2019
- Bench
- R.F. Nariman and Vineet Saran, JJ.
Facts
- NHAI awarded Ssangyong a highway-construction contract.
- The contract contained a price-adjustment formula linked to a specified wholesale price index.
- The original index was later discontinued and replaced by a new series.
- NHAI issued a circular prescribing a method for linking the old and new indices.
- Ssangyong objected that:
- the circular was unilateral;
- it did not form part of the contract;
- and it substantially reduced the price adjustment payable.
- The three-member tribunal produced:
- a majority award accepting NHAI’s circular; and
- a dissenting opinion accepting Ssangyong’s contractual calculation.
- The majority relied on material not properly introduced into the arbitration and effectively substituted the circular for the agreed formula.
- Lower courts declined to set aside the award.
- Ssangyong appealed to the Supreme Court.
Issue
- How the 2015 amendments changed “public policy of India.”
- What constitutes patent illegality after the amendment.
- Whether the tribunal could replace the contract with NHAI’s unilateral circular.
- Whether reliance on material outside the record violated natural justice.
Rule
- After the 2015 amendment:
- “fundamental policy of Indian law” does not permit merits review;
- the broad Western Geco judicial-approach test is removed;
- justice or morality is confined to the most basic notions;
- and patent illegality under Section 34(2A) applies only to domestic awards, not international commercial awards seated in India.
- An award may still be set aside where:
- the tribunal decides contrary to an express contractual provision;
- adopts an impossible interpretation;
- travels beyond the contract;
- gives no reasons;
- or relies on material without giving the parties an opportunity to respond.
- Evidence cannot be reappreciated.
Application
- The tribunal was required to apply the contractual price-adjustment formula.
- NHAI’s circular had never been incorporated through a contractual amendment.
- By using it, the majority tribunal did not merely interpret an ambiguous term.
- It introduced a new bargain.
- The majority also relied upon governmental material and calculations that were not properly placed before the tribunal through the agreed procedure.
- Ssangyong had no meaningful opportunity to meet that material.
- This violated the principle that each party must be given a full opportunity to present its case.
- The Supreme Court held that the award fell outside the parties’ submission and offended the basic contractual foundation of arbitration.
- Since Ssangyong was a foreign company, the arbitration was an international commercial arbitration seated in India.
- Section 34(2A) patent illegality was technically unavailable.
- However, the majority award could still be set aside because:
- it dealt with matters beyond the contract; and
- the procedure violated natural justice.
- Ordinarily, setting aside would require a fresh arbitration.
- In the exceptional circumstances:
- the proceedings had already continued for years;
- the dissenting arbitrator had fully analysed the same issue;
- and both parties consented to the practical solution.
- The Supreme Court used Article 142 to declare the dissenting view operative.
- It clarified that a dissent is not normally an award and cannot routinely be substituted by a Section 34 court.
Conclusion
- The Supreme Court set aside the majority award.
- It held that the tribunal had improperly replaced the contractual formula with a unilateral circular and relied on material outside the proper record.
- By consent and under Article 142, the dissenting result was given effect.
- Use this case for: the controlling post-2015 scope of public policy, natural justice and contractual excess under Section 34.