Judgement Briefs

Alternative Dispute Resolution

Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India

(2019) 15 SCC 131

Citation
(2019) 15 SCC 131
Court
Supreme Court of India
Date
8 May 2019
Bench
R.F. Nariman and Vineet Saran, JJ.

Facts

  • NHAI awarded Ssangyong a highway-construction contract.
  • The contract contained a price-adjustment formula linked to a specified wholesale price index.
  • The original index was later discontinued and replaced by a new series.
  • NHAI issued a circular prescribing a method for linking the old and new indices.
  • Ssangyong objected that:
  • the circular was unilateral;
  • it did not form part of the contract;
  • and it substantially reduced the price adjustment payable.
  • The three-member tribunal produced:
  • a majority award accepting NHAI’s circular; and
  • a dissenting opinion accepting Ssangyong’s contractual calculation.
  • The majority relied on material not properly introduced into the arbitration and effectively substituted the circular for the agreed formula.
  • Lower courts declined to set aside the award.
  • Ssangyong appealed to the Supreme Court.

Issue

  • How the 2015 amendments changed “public policy of India.”
  • What constitutes patent illegality after the amendment.
  • Whether the tribunal could replace the contract with NHAI’s unilateral circular.
  • Whether reliance on material outside the record violated natural justice.

Rule

  • After the 2015 amendment:
  • “fundamental policy of Indian law” does not permit merits review;
  • the broad Western Geco judicial-approach test is removed;
  • justice or morality is confined to the most basic notions;
  • and patent illegality under Section 34(2A) applies only to domestic awards, not international commercial awards seated in India.
  • An award may still be set aside where:
  • the tribunal decides contrary to an express contractual provision;
  • adopts an impossible interpretation;
  • travels beyond the contract;
  • gives no reasons;
  • or relies on material without giving the parties an opportunity to respond.
  • Evidence cannot be reappreciated.

Application

  • The tribunal was required to apply the contractual price-adjustment formula.
  • NHAI’s circular had never been incorporated through a contractual amendment.
  • By using it, the majority tribunal did not merely interpret an ambiguous term.
  • It introduced a new bargain.
  • The majority also relied upon governmental material and calculations that were not properly placed before the tribunal through the agreed procedure.
  • Ssangyong had no meaningful opportunity to meet that material.
  • This violated the principle that each party must be given a full opportunity to present its case.
  • The Supreme Court held that the award fell outside the parties’ submission and offended the basic contractual foundation of arbitration.
  • Since Ssangyong was a foreign company, the arbitration was an international commercial arbitration seated in India.
  • Section 34(2A) patent illegality was technically unavailable.
  • However, the majority award could still be set aside because:
  • it dealt with matters beyond the contract; and
  • the procedure violated natural justice.
  • Ordinarily, setting aside would require a fresh arbitration.
  • In the exceptional circumstances:
  • the proceedings had already continued for years;
  • the dissenting arbitrator had fully analysed the same issue;
  • and both parties consented to the practical solution.
  • The Supreme Court used Article 142 to declare the dissenting view operative.
  • It clarified that a dissent is not normally an award and cannot routinely be substituted by a Section 34 court.

Conclusion

  • The Supreme Court set aside the majority award.
  • It held that the tribunal had improperly replaced the contractual formula with a unilateral circular and relied on material outside the proper record.
  • By consent and under Article 142, the dissenting result was given effect.
  • Use this case for: the controlling post-2015 scope of public policy, natural justice and contractual excess under Section 34.