Judgement Briefs

Alternative Dispute Resolution

State of Orissa v. Damodar Das

AIR 1996 SC 942; (1996) 2 SCC 216

Citation
AIR 1996 SC 942; (1996) 2 SCC 216
Court
Supreme Court of India
Date
15 December 1995
Bench
K. Ramaswamy, Faizan Uddin and B.N. Kirpal, JJ.

Facts

  • Damodar Das was awarded three public works contracts by the State of Orissa concerning water-supply projects.
  • The contracts related to works undertaken during 1967, 1976 and 1977.
  • In some contracts, the contractor completed part of the work and later abandoned it.
  • Measurements were recorded and payments were accepted.
  • On 15 September 1980, the contractor alleged that disputes remained regarding amounts payable under the contracts.
  • He requested the Chief Engineer to appoint or nominate an arbitrator.
  • The Chief Engineer denied that the contracts contained an arbitration clause.
  • Damodar Das then filed applications under Sections 8 and 20 of the Arbitration Act, 1940.
  • The Subordinate Judge appointed arbitrators, and the Orissa High Court upheld that decision.
  • The State appealed to the Supreme Court.
  • It argued that:
  • Clause 25 was only a departmental finality clause;
  • it was not an arbitration agreement; and
  • at least one of the claims was hopelessly barred by limitation.

Issue

  • Whether Clause 25, which made the Public Health Engineer’s decision final, constituted an arbitration agreement.
  • Whether a clause giving an engineer administrative decision-making authority can be treated as an agreement to arbitrate.
  • When limitation begins to run for raising claims through arbitration.

Rule

  • An arbitration agreement requires an express or necessarily implied agreement to submit existing or future disputes to arbitration.
  • Merely declaring that an engineer’s decision on specifications, workmanship, measurements or execution will be final does not automatically create an arbitration agreement.
  • The clause must demonstrate an intention that:
  • disputes between the parties will be adjudicated;
  • the designated person will act judicially or quasi-judicially; and
  • the parties will be bound by the resulting arbitral determination.
  • The Limitation Act applies to arbitration.
  • A cause of arbitration arises when the claimant first becomes entitled to demand arbitration, ordinarily when the underlying claim or dispute arises.
  • A stale claim cannot be revived merely by issuing a fresh arbitration notice many years later.

Application

  • The Court read Clause 25 as a whole rather than isolating the words stating that the engineer’s decision would be “final, conclusive and binding.”
  • The clause authorised the Public Health Engineer to decide questions concerning:
  • specifications and drawings;
  • quality of materials and workmanship;
  • instructions and estimates; and
  • execution or failure to execute the work.
  • These functions were connected with departmental supervision and administration of the construction contract.
  • The clause did not state that:
  • disputes or differences between the contractor and the State would be referred to arbitration;
  • the engineer would hear both parties as an independent adjudicator;
  • the engineer would make an award; or
  • the Arbitration Act would govern the process.
  • The Court therefore refused to infer an arbitration agreement merely because the engineer’s administrative decision was described as final.
  • A finality clause may prevent ordinary contractual questions from being repeatedly reopened, but it does not necessarily transform the deciding officer into an arbitrator.
  • The contractor had also sent his demand to the Chief Engineer requesting appointment of another arbitrator.
  • That conduct itself indicated that he did not regard the Public Health Engineer as the contractually appointed arbitrator.
  • On limitation, the first contract had been completed and payment received in 1967.
  • The contractor waited until September 1980 to raise the claim.
  • The Court held that this claim was hopelessly time-barred.
  • The contractor could not postpone limitation until the date on which the Government formally denied his arbitration request.
  • For the other two contracts, there were disputed facts concerning extensions of time and completion or abandonment of work.
  • Those limitation questions might ordinarily have required adjudication.
  • However, because there was no arbitration agreement at all, no arbitrator could be appointed to decide them.

Conclusion

  • The Supreme Court held that Clause 25 was not an arbitration agreement.
  • It merely conferred administrative and supervisory decision-making authority on the Public Health Engineer.
  • The orders appointing arbitrators were set aside, and the contractor’s applications under Sections 8 and 20 were dismissed.
  • The Court also held that the claim arising from the 1967 contract was barred by limitation.
  • Use this case for: a departmental finality clause is not an arbitration agreement unless it clearly shows an intention to refer disputes for arbitral adjudication.