Alternative Dispute Resolution
State of Orissa v. Damodar Das
AIR 1996 SC 942; (1996) 2 SCC 216
- Citation
- AIR 1996 SC 942; (1996) 2 SCC 216
- Court
- Supreme Court of India
- Date
- 15 December 1995
- Bench
- K. Ramaswamy, Faizan Uddin and B.N. Kirpal, JJ.
Facts
- Damodar Das was awarded three public works contracts by the State of Orissa concerning water-supply projects.
- The contracts related to works undertaken during 1967, 1976 and 1977.
- In some contracts, the contractor completed part of the work and later abandoned it.
- Measurements were recorded and payments were accepted.
- On 15 September 1980, the contractor alleged that disputes remained regarding amounts payable under the contracts.
- He requested the Chief Engineer to appoint or nominate an arbitrator.
- The Chief Engineer denied that the contracts contained an arbitration clause.
- Damodar Das then filed applications under Sections 8 and 20 of the Arbitration Act, 1940.
- The Subordinate Judge appointed arbitrators, and the Orissa High Court upheld that decision.
- The State appealed to the Supreme Court.
- It argued that:
- Clause 25 was only a departmental finality clause;
- it was not an arbitration agreement; and
- at least one of the claims was hopelessly barred by limitation.
Issue
- Whether Clause 25, which made the Public Health Engineer’s decision final, constituted an arbitration agreement.
- Whether a clause giving an engineer administrative decision-making authority can be treated as an agreement to arbitrate.
- When limitation begins to run for raising claims through arbitration.
Rule
- An arbitration agreement requires an express or necessarily implied agreement to submit existing or future disputes to arbitration.
- Merely declaring that an engineer’s decision on specifications, workmanship, measurements or execution will be final does not automatically create an arbitration agreement.
- The clause must demonstrate an intention that:
- disputes between the parties will be adjudicated;
- the designated person will act judicially or quasi-judicially; and
- the parties will be bound by the resulting arbitral determination.
- The Limitation Act applies to arbitration.
- A cause of arbitration arises when the claimant first becomes entitled to demand arbitration, ordinarily when the underlying claim or dispute arises.
- A stale claim cannot be revived merely by issuing a fresh arbitration notice many years later.
Application
- The Court read Clause 25 as a whole rather than isolating the words stating that the engineer’s decision would be “final, conclusive and binding.”
- The clause authorised the Public Health Engineer to decide questions concerning:
- specifications and drawings;
- quality of materials and workmanship;
- instructions and estimates; and
- execution or failure to execute the work.
- These functions were connected with departmental supervision and administration of the construction contract.
- The clause did not state that:
- disputes or differences between the contractor and the State would be referred to arbitration;
- the engineer would hear both parties as an independent adjudicator;
- the engineer would make an award; or
- the Arbitration Act would govern the process.
- The Court therefore refused to infer an arbitration agreement merely because the engineer’s administrative decision was described as final.
- A finality clause may prevent ordinary contractual questions from being repeatedly reopened, but it does not necessarily transform the deciding officer into an arbitrator.
- The contractor had also sent his demand to the Chief Engineer requesting appointment of another arbitrator.
- That conduct itself indicated that he did not regard the Public Health Engineer as the contractually appointed arbitrator.
- On limitation, the first contract had been completed and payment received in 1967.
- The contractor waited until September 1980 to raise the claim.
- The Court held that this claim was hopelessly time-barred.
- The contractor could not postpone limitation until the date on which the Government formally denied his arbitration request.
- For the other two contracts, there were disputed facts concerning extensions of time and completion or abandonment of work.
- Those limitation questions might ordinarily have required adjudication.
- However, because there was no arbitration agreement at all, no arbitrator could be appointed to decide them.
Conclusion
- The Supreme Court held that Clause 25 was not an arbitration agreement.
- It merely conferred administrative and supervisory decision-making authority on the Public Health Engineer.
- The orders appointing arbitrators were set aside, and the contractor’s applications under Sections 8 and 20 were dismissed.
- The Court also held that the claim arising from the 1967 contract was barred by limitation.
- Use this case for: a departmental finality clause is not an arbitration agreement unless it clearly shows an intention to refer disputes for arbitral adjudication.