Contract Law
Cutter v. Powell
(1795) 101 ER 573
- Citation
- (1795) 101 ER 573
- Court
- Court of King's Bench
- Date
- 1795
- Bench
- Lord Kenyon CJ and King's Bench
Facts
- Cutter agreed to serve as second mate on a voyage from Jamaica to Liverpool.
- Powell promised to pay him a fixed lump sum after the ship reached Liverpool.
- The payment promised was substantially higher than the ordinary wage for comparable service.
- The contractual wording made payment dependent upon Cutter continuing, performing his duty and completing the voyage.
- Cutter performed a large portion of the voyage.
- He died before the ship reached Liverpool.
- His widow sought a proportionate part of the promised payment for the period during which he had served.
- Powell resisted the claim, arguing that the contract required complete performance as a condition precedent to payment.
Issue
- Whether Cutter’s estate was entitled to payment for partial performance.
- Whether the contract was an entire contract requiring complete performance before any payment became due.
Rule
- Where a contract promises a lump sum upon complete performance of an entire obligation, complete performance may be a condition precedent to payment.
- If the obligation is entire and indivisible, substantial or partial performance does not automatically create a right to a proportionate price.
- The court must interpret the contract to determine whether:
- payment accrues progressively; or
- payment becomes due only after complete performance.
- Modern doctrines such as substantial performance, quantum meruit and statutory employment protection may soften the rule, but the original case applied the strict entire-obligation principle.
Application
- The payment was not framed as a monthly wage.
- It was a single sum payable after the vessel arrived in Liverpool.
- The unusually high amount indicated that Cutter accepted the risk associated with completion.
- The bargain was therefore not merely an ordinary wage arrangement.
- It was an all-or-nothing promise:
- Cutter would receive the full amount if he completed the voyage;
- nothing became contractually due if the condition was not fulfilled.
- His death was not his fault, and the result was harsh.
- Nevertheless, the Court treated completion as the express basis of the promised payment.
- It refused to rewrite the bargain into a daily or proportional wage agreement.
- The estate could not rely on partial performance because the contract did not apportion the price.
- Nor could it use quantum meruit to contradict the express condition governing remuneration.
Conclusion
- The Court held that Cutter’s widow could not recover a proportionate payment.
- Completion of the voyage was a condition precedent to the lump-sum payment.
- Use this case for: under an entire contract, no payment may become due unless the promised performance is completed.