Contract Law
Energy Watchdog v. Central Electricity Regulatory Commission
(2017) 14 SCC 80; 2017 SCC OnLine SC 378
- Citation
- (2017) 14 SCC 80; 2017 SCC OnLine SC 378
- Court
- Supreme Court of India
- Date
- 2017
- Bench
- P.C. Ghose and R.F. Nariman JJ
Facts
- Indian power-generating companies entered into long-term Power Purchase Agreements with electricity procurers.
- The tariff had been determined through competitive bidding.
- The generating companies expected to use imported Indonesian coal.
- Indonesian regulations later increased the benchmark price of exported coal.
- This substantially increased the generators’ cost of producing electricity.
- The generators sought a compensatory tariff.
- They argued that the change:
- constituted force majeure under the PPAs;
- frustrated the contracts under Section 56;
- alternatively amounted to a change in law.
- The procurers argued that the generators had assumed the commercial risk of fuel-price fluctuation.
Issue
- Whether the increase in the price of Indonesian coal constituted force majeure or frustration.
- Whether a contractual force-majeure clause is governed by Section 32 or Section 56.
Rule
- Where the contract itself contains a force-majeure clause covering the event, the matter is governed by Section 32 as a contingent contractual arrangement.
- Section 56 applies where the supervening event falls outside the contract and makes performance impossible or unlawful.
- Mere increase in cost, hardship or reduced profitability does not amount to frustration.
- A contract is not frustrated merely because performance has become commercially onerous.
- The force-majeure clause must be interpreted strictly according to its wording.
- A foreign-law change is not necessarily “change in law” where the contract defines the expression by reference to Indian law.
Application
- The PPAs contained detailed force-majeure provisions.
- Therefore, the first inquiry was whether the Indonesian regulatory change fell within those clauses.
- The event did not prevent electricity generation or make performance unlawful.
- Coal remained available, although at a higher price.
- The generators’ difficulty was economic rather than physical or legal impossibility.
- The Court held that parties entering fixed-tariff bids assume ordinary commercial risks, including possible fluctuations in fuel cost.
- Section 56 could not be used to rewrite a commercially disadvantageous bargain.
- The Court also rejected the argument that Indonesian regulations constituted a contractual “change in law,” because the relevant clause concerned changes in Indian law.
- The regulatory commission could not award a compensatory tariff outside the contractual framework simply because the original bargain had become less profitable.
- The parties were bound by the risk allocation reflected in the PPAs.
Conclusion
- The Supreme Court held that the rise in imported coal prices did not constitute force majeure or frustration.
- The generators were not entitled to compensatory tariff on that basis.
- Use this case for: commercial hardship or price increase does not frustrate a contract, and contractual force majeure is governed primarily by Section 32.