Judgement Briefs

Contract Law

Energy Watchdog v. Central Electricity Regulatory Commission

(2017) 14 SCC 80; 2017 SCC OnLine SC 378

Citation
(2017) 14 SCC 80; 2017 SCC OnLine SC 378
Court
Supreme Court of India
Date
2017
Bench
P.C. Ghose and R.F. Nariman JJ

Facts

  • Indian power-generating companies entered into long-term Power Purchase Agreements with electricity procurers.
  • The tariff had been determined through competitive bidding.
  • The generating companies expected to use imported Indonesian coal.
  • Indonesian regulations later increased the benchmark price of exported coal.
  • This substantially increased the generators’ cost of producing electricity.
  • The generators sought a compensatory tariff.
  • They argued that the change:
  • constituted force majeure under the PPAs;
  • frustrated the contracts under Section 56;
  • alternatively amounted to a change in law.
  • The procurers argued that the generators had assumed the commercial risk of fuel-price fluctuation.

Issue

  • Whether the increase in the price of Indonesian coal constituted force majeure or frustration.
  • Whether a contractual force-majeure clause is governed by Section 32 or Section 56.

Rule

  • Where the contract itself contains a force-majeure clause covering the event, the matter is governed by Section 32 as a contingent contractual arrangement.
  • Section 56 applies where the supervening event falls outside the contract and makes performance impossible or unlawful.
  • Mere increase in cost, hardship or reduced profitability does not amount to frustration.
  • A contract is not frustrated merely because performance has become commercially onerous.
  • The force-majeure clause must be interpreted strictly according to its wording.
  • A foreign-law change is not necessarily “change in law” where the contract defines the expression by reference to Indian law.

Application

  • The PPAs contained detailed force-majeure provisions.
  • Therefore, the first inquiry was whether the Indonesian regulatory change fell within those clauses.
  • The event did not prevent electricity generation or make performance unlawful.
  • Coal remained available, although at a higher price.
  • The generators’ difficulty was economic rather than physical or legal impossibility.
  • The Court held that parties entering fixed-tariff bids assume ordinary commercial risks, including possible fluctuations in fuel cost.
  • Section 56 could not be used to rewrite a commercially disadvantageous bargain.
  • The Court also rejected the argument that Indonesian regulations constituted a contractual “change in law,” because the relevant clause concerned changes in Indian law.
  • The regulatory commission could not award a compensatory tariff outside the contractual framework simply because the original bargain had become less profitable.
  • The parties were bound by the risk allocation reflected in the PPAs.

Conclusion

  • The Supreme Court held that the rise in imported coal prices did not constitute force majeure or frustration.
  • The generators were not entitled to compensatory tariff on that basis.
  • Use this case for: commercial hardship or price increase does not frustrate a contract, and contractual force majeure is governed primarily by Section 32.