Judgement Briefs

Contract Law

Hindustan Steelworks Construction Ltd. v. Tarapore & Co.

(1996) 5 SCC 34

Citation
(1996) 5 SCC 34
Court
Supreme Court of India
Date
1996
Bench
K. Ramaswamy and other JJ

Facts

  • Hindustan Steelworks awarded Tarapore & Co. a major construction contract.
  • The work was repeatedly delayed and later reduced by agreement.
  • Bank of India issued several guarantees at Tarapore’s request in favour of Hindustan Steelworks.
  • The guarantees stated that:
  • the Bank would pay without demur;
  • Hindustan Steelworks would decide whether breach had occurred;
  • its assessment of loss would bind the Bank;
  • underlying disputes would not affect payment.
  • Hindustan Steelworks terminated the contract and invoked the guarantees.
  • Tarapore sought an injunction, arguing that:
  • disputes were pending before arbitrators;
  • breach and damages had not yet been adjudicated.
  • The High Court restrained encashment.

Issue

  • Whether an unconditional bank guarantee can be restrained because the underlying contractual dispute remains pending.
  • Whether the beneficiary must first establish breach and quantify damages before invocation.

Rule

  • A bank guarantee is an independent contract between the bank and the beneficiary.
  • An unconditional guarantee must ordinarily be honoured according to its terms, regardless of disputes under the underlying contract.
  • Courts interfere only in exceptional cases, principally:
  • egregious fraud of which the bank has notice; or
  • irretrievable injustice or equivalent exceptional circumstances.
  • Pending arbitration and disputed breach do not by themselves justify an injunction.

Application

  • The operative clauses made the guarantees payable on demand and without demur.
  • Hindustan Steelworks was expressly made the judge of whether the contractor had committed breach and of the amount payable.
  • The Bank’s obligation did not depend on an arbitral award.
  • The High Court incorrectly merged:
  • the contractor’s liability under the works contract; and
  • the Bank’s independent obligation under the guarantees.
  • Tarapore could pursue its contractual claims in arbitration and later recover any amount wrongfully retained.
  • That did not permit it to stop immediate payment by the Bank.
  • No fraud in the guarantees was established.
  • Nor was there irretrievable injustice of the exceptional kind required.
  • The Supreme Court therefore restored the autonomy and commercial certainty of the guarantees.

Conclusion

  • The Supreme Court allowed Hindustan Steelworks’ appeal and removed the injunction.
  • The guarantees could be encashed immediately.
  • Use this case for: an unconditional bank guarantee is autonomous and cannot be restrained merely because breach or damages are disputed in arbitration.