Contract Law
Hindustan Steelworks Construction Ltd. v. Tarapore & Co.
(1996) 5 SCC 34
- Citation
- (1996) 5 SCC 34
- Court
- Supreme Court of India
- Date
- 1996
- Bench
- K. Ramaswamy and other JJ
Facts
- Hindustan Steelworks awarded Tarapore & Co. a major construction contract.
- The work was repeatedly delayed and later reduced by agreement.
- Bank of India issued several guarantees at Tarapore’s request in favour of Hindustan Steelworks.
- The guarantees stated that:
- the Bank would pay without demur;
- Hindustan Steelworks would decide whether breach had occurred;
- its assessment of loss would bind the Bank;
- underlying disputes would not affect payment.
- Hindustan Steelworks terminated the contract and invoked the guarantees.
- Tarapore sought an injunction, arguing that:
- disputes were pending before arbitrators;
- breach and damages had not yet been adjudicated.
- The High Court restrained encashment.
Issue
- Whether an unconditional bank guarantee can be restrained because the underlying contractual dispute remains pending.
- Whether the beneficiary must first establish breach and quantify damages before invocation.
Rule
- A bank guarantee is an independent contract between the bank and the beneficiary.
- An unconditional guarantee must ordinarily be honoured according to its terms, regardless of disputes under the underlying contract.
- Courts interfere only in exceptional cases, principally:
- egregious fraud of which the bank has notice; or
- irretrievable injustice or equivalent exceptional circumstances.
- Pending arbitration and disputed breach do not by themselves justify an injunction.
Application
- The operative clauses made the guarantees payable on demand and without demur.
- Hindustan Steelworks was expressly made the judge of whether the contractor had committed breach and of the amount payable.
- The Bank’s obligation did not depend on an arbitral award.
- The High Court incorrectly merged:
- the contractor’s liability under the works contract; and
- the Bank’s independent obligation under the guarantees.
- Tarapore could pursue its contractual claims in arbitration and later recover any amount wrongfully retained.
- That did not permit it to stop immediate payment by the Bank.
- No fraud in the guarantees was established.
- Nor was there irretrievable injustice of the exceptional kind required.
- The Supreme Court therefore restored the autonomy and commercial certainty of the guarantees.
Conclusion
- The Supreme Court allowed Hindustan Steelworks’ appeal and removed the injunction.
- The guarantees could be encashed immediately.
- Use this case for: an unconditional bank guarantee is autonomous and cannot be restrained merely because breach or damages are disputed in arbitration.