Contract Law
Murlidhar Chiranjilal v. Harishchandra Dwarkadas
AIR 1962 SC 366; [1962] 1 SCR 653
- Citation
- AIR 1962 SC 366; [1962] 1 SCR 653
- Court
- Supreme Court of India
- Date
- 1961
- Bench
- Supreme Court Bench
Facts
- The parties entered into a contract for the sale and delivery of canvas.
- The seller failed to deliver the agreed goods.
- The buyer claimed compensation for breach.
- The dispute concerned the correct method of calculating damages under Section 73 of the Indian Contract Act.
- The buyer sought recovery based on the loss allegedly suffered because the goods were not supplied.
Issue
- What is the correct measure of damages for failure to deliver goods?
- Whether damages should be based upon the difference between the contractual price and market price at the time of breach.
Rule
- Section 73 incorporates the principles stated in Hadley v. Baxendale.
- Compensation is available for loss that:
- naturally arose in the usual course from the breach; or
- was within the parties’ contemplation when they contracted.
- Remote or indirect loss is not recoverable.
- In an ordinary sale of goods, the usual measure is:
- Market price on the date of breach − contract price.
- The claimant must also take reasonable steps to mitigate loss.
Application
- The object of damages was not to punish the defaulting seller.
- The buyer was entitled only to the actual financial difference produced by non-delivery.
- If substitute goods could have been purchased in the market, the buyer should ordinarily have purchased them.
- The loss would then be represented by the additional amount reasonably required to obtain replacement goods.
- The relevant market price was the price at the contractual place and time for delivery.
- A later rise in prices could not automatically be charged to the seller because the buyer could have reduced that loss by purchasing promptly after breach.
- The Court also emphasised that Section 73 contains two connected principles:
- remoteness, determining which kinds of loss are recoverable;
- mitigation, preventing recovery of avoidable loss.
- The buyer had to prove the relevant market rate and could not obtain speculative or unsupported compensation.
- Where no market existed, another reasonable method could be used, but the underlying purpose remained compensation for actual loss.
Conclusion
- The Supreme Court held that the ordinary measure was the difference between the contract price and the market price on the date of breach.
- Loss that could reasonably have been avoided was not recoverable.
- Use this case for: Section 73 follows Hadley v. Baxendale and ordinarily measures non-delivery damages by the market-price differential.