Judgement Briefs

Contract Law

Ruxley Electronics and Construction Ltd. v. Forsyth

[1996] AC 344

Citation
[1996] AC 344
Court
House of Lords
Date
1995
Bench
Lord Bridge and other Law Lords

Facts

  • Ruxley agreed to construct a swimming pool for Forsyth.
  • The contract required the pool’s diving area to be 7 feet 6 inches deep.
  • The completed pool was shallower than specified.
  • The pool was nevertheless:
  • safe for diving;
  • usable;
  • not reduced in market value.
  • Forsyth claimed the entire cost of demolishing and rebuilding the pool.
  • Rebuilding would cost substantially more than the benefit obtained from correcting the depth.
  • Evidence suggested that Forsyth did not genuinely intend to reconstruct the pool.

Issue

  • Whether damages should equal the full cost of curing the defect.
  • Whether loss of amenity could be awarded where neither market value nor reasonable cost of cure reflected the true loss.

Rule

  • The normal objective is to protect the expectation interest.
  • Possible measures include:
  • diminution in value;
  • reasonable cost of cure;
  • damages for loss of amenity.
  • Cost of cure is inappropriate where it is wholly disproportionate to the benefit obtained.
  • The claimant’s intention to undertake remedial work may be relevant to reasonableness.
  • A contractual promise may possess personal value even where breach causes no market-value reduction.

Application

  • Ruxley had clearly breached the contract by failing to provide the specified depth.
  • However, awarding the full reconstruction cost would produce economic waste.
  • The pool was safe and functional.
  • Correcting the defect required destruction of a usable structure for a relatively limited personal benefit.
  • A nominal award would also be inadequate because Forsyth had genuinely contracted for a deeper pool.
  • The House of Lords therefore recognised a middle measure: loss of amenity.
  • This compensated Forsyth for not receiving the exact performance promised without granting a disproportionate windfall.
  • The measure of damages must be reasonable and proportionate to the actual contractual interest injured.

Conclusion

  • Forsyth was denied the full cost of reconstruction.
  • He received £2,500 for loss of amenity.
  • Use this case for: cost of cure will be refused where disproportionate, but loss of amenity may compensate the unfulfilled contractual expectation.