Contract Law
Ruxley Electronics and Construction Ltd. v. Forsyth
[1996] AC 344
- Citation
- [1996] AC 344
- Court
- House of Lords
- Date
- 1995
- Bench
- Lord Bridge and other Law Lords
Facts
- Ruxley agreed to construct a swimming pool for Forsyth.
- The contract required the pool’s diving area to be 7 feet 6 inches deep.
- The completed pool was shallower than specified.
- The pool was nevertheless:
- safe for diving;
- usable;
- not reduced in market value.
- Forsyth claimed the entire cost of demolishing and rebuilding the pool.
- Rebuilding would cost substantially more than the benefit obtained from correcting the depth.
- Evidence suggested that Forsyth did not genuinely intend to reconstruct the pool.
Issue
- Whether damages should equal the full cost of curing the defect.
- Whether loss of amenity could be awarded where neither market value nor reasonable cost of cure reflected the true loss.
Rule
- The normal objective is to protect the expectation interest.
- Possible measures include:
- diminution in value;
- reasonable cost of cure;
- damages for loss of amenity.
- Cost of cure is inappropriate where it is wholly disproportionate to the benefit obtained.
- The claimant’s intention to undertake remedial work may be relevant to reasonableness.
- A contractual promise may possess personal value even where breach causes no market-value reduction.
Application
- Ruxley had clearly breached the contract by failing to provide the specified depth.
- However, awarding the full reconstruction cost would produce economic waste.
- The pool was safe and functional.
- Correcting the defect required destruction of a usable structure for a relatively limited personal benefit.
- A nominal award would also be inadequate because Forsyth had genuinely contracted for a deeper pool.
- The House of Lords therefore recognised a middle measure: loss of amenity.
- This compensated Forsyth for not receiving the exact performance promised without granting a disproportionate windfall.
- The measure of damages must be reasonable and proportionate to the actual contractual interest injured.
Conclusion
- Forsyth was denied the full cost of reconstruction.
- He received £2,500 for loss of amenity.
- Use this case for: cost of cure will be refused where disproportionate, but loss of amenity may compensate the unfulfilled contractual expectation.