Contract Law
Satyabrata Ghose v. Mugneeram Bangur & Co.
AIR 1954 SC 44; 1954 SCR 310
- Citation
- AIR 1954 SC 44; 1954 SCR 310
- Court
- Supreme Court of India
- Date
- 1953
- Bench
- B.K. Mukherjea and other JJ
Facts
- Mugneeram Bangur & Co. developed a residential scheme near Calcutta.
- It agreed to sell a plot to Satyabrata Ghose.
- The developer was required to construct roads and drains before completing conveyance.
- During the Second World War, the Government requisitioned a substantial portion of the scheme’s land for military purposes.
- The developer informed the purchaser that performance had become impossible and treated the contract as cancelled.
- It offered to return the money paid.
- The purchaser insisted that the contract remained alive and sought enforcement.
- The developer relied on Section 56 and claimed frustration.
Issue
- Whether temporary governmental requisition of the land frustrated the agreement for sale.
- What “impossible” means under Section 56.
Rule
- Section 56 embodies the Indian law of frustration and is not merely a rule of implied terms.
- “Impossible” does not mean only literal or physical impossibility.
- Performance may be legally impossible where a supervening event:
- destroys the foundation of the contract; or
- makes performance fundamentally different from what the parties contemplated.
- However:
- temporary delay;
- inconvenience;
- increased expense;
- interruption that does not destroy the contract’s object, will not ordinarily amount to frustration.
- The contract and surrounding circumstances must be considered as a whole.
Application
- The requisition did not permanently destroy the land.
- Ownership remained with the developer.
- The requisition was connected to wartime needs and could end later.
- The contract did not prescribe a strict completion date.
- The development scheme was large and naturally involved time for construction of roads and drains.
- Therefore, delay was not necessarily fatal to the bargain.
- The central object was transfer of the identified plot after development.
- That object had not become impossible or fundamentally transformed.
- The Court rejected an overly narrow interpretation of “impossible,” but equally refused to treat every serious delay as frustration.
- The developer had not proved that the requisition would continue so long that the purpose of the agreement was destroyed.
- Performance remained capable of being resumed once the requisition ended.
Conclusion
- The Supreme Court held that the contract was not frustrated.
- Temporary requisition merely delayed performance and did not destroy the agreement’s foundation.
- Use this case for: Section 56 covers practical impossibility, but temporary delay frustrates a contract only where it destroys the contract’s essential object.