Contract Law
Transfield Shipping Inc. v. Mercator Shipping Inc.
[2008] UKHL 48; [2009] 1 AC 61
- Citation
- [2008] UKHL 48; [2009] 1 AC 61
- Court
- House of Lords
- Date
- 2008
- Bench
- Lord Hoffmann and other Law Lords
Facts
- Mercator chartered its vessel, The Achilleas, to Transfield.
- Transfield was required to return the vessel by a specified date.
- It returned the vessel approximately nine days late.
- During the charter, Mercator had agreed to a profitable follow-on charter with another party.
- Because of the delay, the next charterer demanded a reduction in the hire rate for the entire subsequent charter period.
- Market rates had fallen sharply.
- Mercator accepted the reduced rate and claimed the entire loss from Transfield.
- The claimed loss was far greater than the ordinary market difference for the nine-day overrun.
Issue
- Whether the late-returning charterer was liable for the entire reduced income under the subsequent charter.
- Whether reasonable foreseeability alone determines remoteness.
Rule
- Hadley v. Baxendale remains the starting point.
- A foreseeable kind of loss may nevertheless be unrecoverable where, objectively construed, the defendant cannot reasonably be regarded as having assumed responsibility for that risk.
- The court must consider:
- commercial background;
- market understanding;
- contractual allocation of risk;
- proportionality between breach and alleged liability.
- The assumption-of-responsibility analysis is especially relevant where market practice indicates a narrower liability.
Application
- A charterer would ordinarily know that late delivery could prevent the owner from using the vessel elsewhere.
- Therefore, loss for the period of the overrun was foreseeable.
- However, the extraordinary loss claimed arose because:
- a separate future charter had been negotiated;
- the market collapsed;
- the next charterer required a reduced rate for months, not merely nine days.
- Evidence of shipping-market practice showed that damages for late return were ordinarily calculated by comparing:
- the charter rate; and
- the market rate, for the actual period of delay.
- A reasonable charterer would not normally understand that a short delay exposed it to fluctuations affecting an entire later charter.
- The majority therefore considered that Transfield had not assumed responsibility for that exceptional risk.
- The case does not abandon foreseeability.
- It adds that foreseeability must sometimes be assessed through the contractual and commercial allocation of responsibility.
Conclusion
- Transfield was liable only for the market-rate difference during the nine-day overrun.
- It was not liable for the entire loss under the subsequent charter.
- Use this case for: a foreseeable loss may still be too remote where the defendant did not objectively assume responsibility for it.