Judgement Briefs

Contract Law

Transfield Shipping Inc. v. Mercator Shipping Inc.

[2008] UKHL 48; [2009] 1 AC 61

Citation
[2008] UKHL 48; [2009] 1 AC 61
Court
House of Lords
Date
2008
Bench
Lord Hoffmann and other Law Lords

Facts

  • Mercator chartered its vessel, The Achilleas, to Transfield.
  • Transfield was required to return the vessel by a specified date.
  • It returned the vessel approximately nine days late.
  • During the charter, Mercator had agreed to a profitable follow-on charter with another party.
  • Because of the delay, the next charterer demanded a reduction in the hire rate for the entire subsequent charter period.
  • Market rates had fallen sharply.
  • Mercator accepted the reduced rate and claimed the entire loss from Transfield.
  • The claimed loss was far greater than the ordinary market difference for the nine-day overrun.

Issue

  • Whether the late-returning charterer was liable for the entire reduced income under the subsequent charter.
  • Whether reasonable foreseeability alone determines remoteness.

Rule

  • Hadley v. Baxendale remains the starting point.
  • A foreseeable kind of loss may nevertheless be unrecoverable where, objectively construed, the defendant cannot reasonably be regarded as having assumed responsibility for that risk.
  • The court must consider:
  • commercial background;
  • market understanding;
  • contractual allocation of risk;
  • proportionality between breach and alleged liability.
  • The assumption-of-responsibility analysis is especially relevant where market practice indicates a narrower liability.

Application

  • A charterer would ordinarily know that late delivery could prevent the owner from using the vessel elsewhere.
  • Therefore, loss for the period of the overrun was foreseeable.
  • However, the extraordinary loss claimed arose because:
  • a separate future charter had been negotiated;
  • the market collapsed;
  • the next charterer required a reduced rate for months, not merely nine days.
  • Evidence of shipping-market practice showed that damages for late return were ordinarily calculated by comparing:
  • the charter rate; and
  • the market rate, for the actual period of delay.
  • A reasonable charterer would not normally understand that a short delay exposed it to fluctuations affecting an entire later charter.
  • The majority therefore considered that Transfield had not assumed responsibility for that exceptional risk.
  • The case does not abandon foreseeability.
  • It adds that foreseeability must sometimes be assessed through the contractual and commercial allocation of responsibility.

Conclusion

  • Transfield was liable only for the market-rate difference during the nine-day overrun.
  • It was not liable for the entire loss under the subsequent charter.
  • Use this case for: a foreseeable loss may still be too remote where the defendant did not objectively assume responsibility for it.