Contract Law
Williams v. Roffey Bros. & Nicholls (Contractors) Ltd.
[1991] 1 QB 1
- Citation
- [1991] 1 QB 1
- Court
- Court of Appeal of England and Wales
- Date
- 1990
- Bench
- Glidewell, Russell and Purchas LJJ
Facts
- Roffey Brothers had a building contract to renovate flats.
- The main contract contained a penalty clause for delay.
- Roffey subcontracted carpentry work to Williams for a fixed price.
- Williams later experienced financial difficulty because he had underpriced the work.
- He could not continue efficiently at the original price.
- Roffey became concerned that:
- Williams might stop work;
- the project would be delayed;
- Roffey would have to find another carpenter;
- Roffey might incur the main contract’s delay penalty.
- Roffey therefore promised to pay Williams an additional amount for completing the work on time.
- Williams continued working but was not paid the full additional amount.
- Roffey argued that the promise was unsupported by consideration because Williams was already contractually bound to perform the carpentry work.
Issue
- Whether performance of an existing contractual duty can amount to consideration for a promise of additional payment.
- Whether the promisor’s practical benefit can constitute sufficient consideration.
Rule
- Traditionally, performance of an existing contractual duty is not fresh consideration.
- However, where:
- A has a contract with B;
- B doubts whether A will complete;
- B promises additional payment;
- B obtains a practical benefit or avoids a practical disadvantage;
- the promise is not obtained by fraud or economic duress; then the practical benefit may amount to sufficient consideration.
- Consideration need not be a new legal right if the promisor receives a real commercial benefit.
Application
- Williams did not promise work fundamentally different from what he had already agreed to perform.
- Under the traditional rule in Stilk v. Myrick, this would suggest no fresh consideration.
- However, the Court examined the commercial reality.
- Roffey received several practical benefits from promising additional payment:
- better prospects of timely completion;
- avoidance of the trouble and cost of finding a replacement carpenter;
- avoidance of disruption to other trades;
- reduced risk of liability under the penalty clause;
- a more organised payment system based on completed flats.
- These benefits were real and commercially valuable even though Williams’ formal legal duty remained unchanged.
- The Court also found no fraud or economic duress.
- Williams had not deliberately created the difficulty to force more money from Roffey.
- Roffey voluntarily offered the additional payment because it was commercially advantageous.
- Therefore, the agreement was not a coerced modification.
- The case did not abolish the pre-existing duty rule entirely.
- Instead, it recognised that a practical benefit may be sufficient consideration where the renegotiation is genuine and untainted by pressure.
- The case is particularly important in modern commercial contracts, where parties often vary agreements to avoid delay, disruption or greater loss.
Conclusion
- The Court of Appeal held that Roffey’s promise of additional payment was supported by consideration.
- Roffey obtained a practical benefit and avoided significant commercial disadvantages.
- Williams was entitled to the additional payment for the work completed.
- Use this case for: a practical benefit may constitute consideration for a promise to pay more, provided there is no fraud or economic duress.