Judgement Briefs

Contract Law

Williams v. Roffey Bros. & Nicholls (Contractors) Ltd.

[1991] 1 QB 1

Citation
[1991] 1 QB 1
Court
Court of Appeal of England and Wales
Date
1990
Bench
Glidewell, Russell and Purchas LJJ

Facts

  • Roffey Brothers had a building contract to renovate flats.
  • The main contract contained a penalty clause for delay.
  • Roffey subcontracted carpentry work to Williams for a fixed price.
  • Williams later experienced financial difficulty because he had underpriced the work.
  • He could not continue efficiently at the original price.
  • Roffey became concerned that:
  • Williams might stop work;
  • the project would be delayed;
  • Roffey would have to find another carpenter;
  • Roffey might incur the main contract’s delay penalty.
  • Roffey therefore promised to pay Williams an additional amount for completing the work on time.
  • Williams continued working but was not paid the full additional amount.
  • Roffey argued that the promise was unsupported by consideration because Williams was already contractually bound to perform the carpentry work.

Issue

  • Whether performance of an existing contractual duty can amount to consideration for a promise of additional payment.
  • Whether the promisor’s practical benefit can constitute sufficient consideration.

Rule

  • Traditionally, performance of an existing contractual duty is not fresh consideration.
  • However, where:
  • A has a contract with B;
  • B doubts whether A will complete;
  • B promises additional payment;
  • B obtains a practical benefit or avoids a practical disadvantage;
  • the promise is not obtained by fraud or economic duress; then the practical benefit may amount to sufficient consideration.
  • Consideration need not be a new legal right if the promisor receives a real commercial benefit.

Application

  • Williams did not promise work fundamentally different from what he had already agreed to perform.
  • Under the traditional rule in Stilk v. Myrick, this would suggest no fresh consideration.
  • However, the Court examined the commercial reality.
  • Roffey received several practical benefits from promising additional payment:
  • better prospects of timely completion;
  • avoidance of the trouble and cost of finding a replacement carpenter;
  • avoidance of disruption to other trades;
  • reduced risk of liability under the penalty clause;
  • a more organised payment system based on completed flats.
  • These benefits were real and commercially valuable even though Williams’ formal legal duty remained unchanged.
  • The Court also found no fraud or economic duress.
  • Williams had not deliberately created the difficulty to force more money from Roffey.
  • Roffey voluntarily offered the additional payment because it was commercially advantageous.
  • Therefore, the agreement was not a coerced modification.
  • The case did not abolish the pre-existing duty rule entirely.
  • Instead, it recognised that a practical benefit may be sufficient consideration where the renegotiation is genuine and untainted by pressure.
  • The case is particularly important in modern commercial contracts, where parties often vary agreements to avoid delay, disruption or greater loss.

Conclusion

  • The Court of Appeal held that Roffey’s promise of additional payment was supported by consideration.
  • Roffey obtained a practical benefit and avoided significant commercial disadvantages.
  • Williams was entitled to the additional payment for the work completed.
  • Use this case for: a practical benefit may constitute consideration for a promise to pay more, provided there is no fraud or economic duress.