Environmental Law
Alembic Pharmaceuticals Ltd. v. Rohit Prajapati
(2020) 17 SCC 157
- Citation
- (2020) 17 SCC 157
- Court
- Supreme Court of India
- Date
- 1 Apr 2020
- Bench
- D.Y. Chandrachud & Ajay Rastogi, JJ.
Facts
- Several pharmaceutical and chemical industries in Gujarat expanded production without first obtaining the environmental clearance required under the EIA Notification.
- They had other pollution-control permissions, but lacked prior EC for the expanded capacity.
- The Ministry later considered applications for ex post facto environmental clearance.
- The NGT criticised the violations and directed action.
- The industries argued that:
- the units had operated for years;
- substantial investments had been made;
- workers depended upon them;
- later appraisal had found them capable of environmental compliance.
- Environmental groups argued that allowing later clearance would destroy the preventive purpose of EIA.
Issue
- Whether environmental clearance may ordinarily be granted after a project has already begun operating.
- Whether closure was the only possible consequence of operating without prior EC.
- What remedy was appropriate where projects subsequently underwent environmental appraisal.
Rule
- Prior environmental clearance is central to the EIA regime.
- EIA is anticipatory:
- impacts must be studied before construction or expansion;
- alternatives must be considered before irreversible commitment;
- public participation must occur before the project becomes a fait accompli.
- Routine ex post facto clearance is contrary to the precautionary principle.
- Courts may nevertheless mould relief under Article 142 in exceptional circumstances.
- Environmental violations require meaningful consequences, including restoration and deterrent compensation.
Application
- The Court clearly rejected the idea that ex post facto EC could become a normal administrative practice.
- A project proponent cannot:
- construct first;
- create employment and investment;
- then demand regularisation because closure has become difficult.
- Such a system would reward deliberate non-compliance.
- It would also deprive the EAC and public of the opportunity to influence:
- site selection;
- technology;
- scale;
- pollution controls;
- alternatives.
- However, the Court considered the factual position of the particular industries.
- They had subsequently obtained environmental clearances after appraisal.
- There was no finding that their continued operation was environmentally impossible.
- Immediate closure could:
- eliminate employment;
- destroy major productive assets;
- produce waste without necessarily improving environmental outcomes.
- The Court therefore separated:
- the illegality of operating without prior EC; and
- the most proportionate remedy.
- It imposed substantial financial liability for ecological restoration and deterrence instead of ordering permanent closure.
- This did not validate the concept of routine post-facto clearance.
- It was an exceptional exercise of judicial power based on the completed appraisal and existing circumstances.
Conclusion
- The Supreme Court held that ex post facto environmental clearance is fundamentally inconsistent with the EIA Notification’s preventive structure.
- Prior EC remains the legal rule.
- On the special facts, the Court did not close the units because they had later undergone appraisal and received EC.
- It imposed substantial environmental compensation upon the industries for restoration and for the period of unlawful operation.
- The judgment must not be read as giving developers a right to regularisation.
- Use this case for: the illegality of routine ex post facto EC and the possibility of exceptional, heavily penalised relief.