Judgement Briefs

Environmental Law

Alembic Pharmaceuticals Ltd. v. Rohit Prajapati

(2020) 17 SCC 157

Citation
(2020) 17 SCC 157
Court
Supreme Court of India
Date
1 Apr 2020
Bench
D.Y. Chandrachud & Ajay Rastogi, JJ.

Facts

  • Several pharmaceutical and chemical industries in Gujarat expanded production without first obtaining the environmental clearance required under the EIA Notification.
  • They had other pollution-control permissions, but lacked prior EC for the expanded capacity.
  • The Ministry later considered applications for ex post facto environmental clearance.
  • The NGT criticised the violations and directed action.
  • The industries argued that:
  • the units had operated for years;
  • substantial investments had been made;
  • workers depended upon them;
  • later appraisal had found them capable of environmental compliance.
  • Environmental groups argued that allowing later clearance would destroy the preventive purpose of EIA.

Issue

  • Whether environmental clearance may ordinarily be granted after a project has already begun operating.
  • Whether closure was the only possible consequence of operating without prior EC.
  • What remedy was appropriate where projects subsequently underwent environmental appraisal.

Rule

  • Prior environmental clearance is central to the EIA regime.
  • EIA is anticipatory:
  • impacts must be studied before construction or expansion;
  • alternatives must be considered before irreversible commitment;
  • public participation must occur before the project becomes a fait accompli.
  • Routine ex post facto clearance is contrary to the precautionary principle.
  • Courts may nevertheless mould relief under Article 142 in exceptional circumstances.
  • Environmental violations require meaningful consequences, including restoration and deterrent compensation.

Application

  • The Court clearly rejected the idea that ex post facto EC could become a normal administrative practice.
  • A project proponent cannot:
  • construct first;
  • create employment and investment;
  • then demand regularisation because closure has become difficult.
  • Such a system would reward deliberate non-compliance.
  • It would also deprive the EAC and public of the opportunity to influence:
  • site selection;
  • technology;
  • scale;
  • pollution controls;
  • alternatives.
  • However, the Court considered the factual position of the particular industries.
  • They had subsequently obtained environmental clearances after appraisal.
  • There was no finding that their continued operation was environmentally impossible.
  • Immediate closure could:
  • eliminate employment;
  • destroy major productive assets;
  • produce waste without necessarily improving environmental outcomes.
  • The Court therefore separated:
  • the illegality of operating without prior EC; and
  • the most proportionate remedy.
  • It imposed substantial financial liability for ecological restoration and deterrence instead of ordering permanent closure.
  • This did not validate the concept of routine post-facto clearance.
  • It was an exceptional exercise of judicial power based on the completed appraisal and existing circumstances.

Conclusion

  • The Supreme Court held that ex post facto environmental clearance is fundamentally inconsistent with the EIA Notification’s preventive structure.
  • Prior EC remains the legal rule.
  • On the special facts, the Court did not close the units because they had later undergone appraisal and received EC.
  • It imposed substantial environmental compensation upon the industries for restoration and for the period of unlawful operation.
  • The judgment must not be read as giving developers a right to regularisation.
  • Use this case for: the illegality of routine ex post facto EC and the possibility of exceptional, heavily penalised relief.