Environmental Law
Hanuman Laxman Aroskar v. Union of India - Mopa Airport Case II
(2020) 12 SCC 1
- Citation
- (2020) 12 SCC 1
- Court
- Supreme Court of India
- Date
- 16 Jan 2020
- Bench
- D.Y. Chandrachud & Ajay Rastogi, JJ.
Facts
- Following the 2019 judgment, the EAC reconsidered the Mopa Airport proposal.
- It examined additional material concerning:
- biodiversity;
- trees;
- water;
- drainage;
- carbon emissions;
- local ecological conditions.
- The EAC recommended continuation of the project with a large number of additional conditions.
- These included:
- biodiversity conservation;
- water-management safeguards;
- monitoring;
- a zero-carbon or low-carbon programme;
- institutional supervision.
- Objections were raised that:
- the fresh appraisal remained inadequate;
- some experts lacked independence;
- the conditions did not cure the original defects.
- The matter returned to the Supreme Court.
Issue
- Whether the reconsideration genuinely complied with the 2019 directions.
- Whether the additional safeguards were sufficient to lift the suspension.
- Whether objections to the composition and expertise of the EAC invalidated the fresh decision.
Rule
- Where a clearance is suspended for procedural and substantive defects, the authority must undertake genuine reconsideration rather than mechanically repeat its earlier conclusion.
- Courts examine:
- whether relevant material was considered;
- whether reasons were recorded;
- whether meaningful additional safeguards were imposed.
- Judicial review focuses upon legality and rationality of expert decision-making.
- Courts ordinarily do not substitute their own environmental design where a competent expert body has lawfully reconsidered the matter.
Application
- The Court compared the fresh appraisal with the deficiencies identified in 2019.
- It found that the EAC had now considered substantially more material.
- The additional conditions were not merely routine.
- They addressed:
- conservation of local flora and fauna;
- water recharge;
- construction impacts;
- compensatory planting;
- carbon management;
- continuous compliance.
- The Court accepted that every environmental risk could not be eliminated from a major infrastructure project.
- The legal requirement was to identify, minimise and monitor those risks through enforceable conditions.
- The argument concerning expert composition was examined, but the Court did not find sufficient material to invalidate the entire process.
- It also considered the role of post-clearance monitoring.
- Environmental safeguards cannot remain promises on paper.
- Independent technical supervision was therefore essential.
- NEERI was given an important monitoring role.
- The Court linked permission to proceed with compliance with:
- the original EC conditions;
- the conditions imposed by the NGT;
- the new EAC conditions.
- Thus, lifting the suspension did not erase the project proponent’s environmental obligations.
- It increased them.
- The decision illustrates the difference between:
- curing an appraisal defect before construction resumes; and
- granting an unrestricted post-facto approval after environmental damage.
Conclusion
- The Supreme Court lifted the suspension of the environmental clearance.
- Construction was permitted to proceed subject to the complete set of original and additional conditions.
- NEERI was directed to monitor compliance and report violations.
- The project proponent remained bound by the enhanced ecological and carbon-related safeguards.
- The Court concluded that the reconsideration sufficiently complied with the 2019 order.
- This second judgment therefore validates the project only after corrective expert appraisal and enforceable monitoring.
- Use this case for: curing defects through genuine reappraisal and allowing a project to proceed under strengthened, monitored conditions.