Environmental Law
Lafarge Umiam Mining Pvt. Ltd. v. Union of India
(2011) 7 SCC 338
- Citation
- (2011) 7 SCC 338
- Court
- Supreme Court of India
- Date
- 6 Jul 2011
- Bench
- S.H. Kapadia, CJI; Aftab Alam & K.S. Radhakrishnan, JJ.
Facts
- Lafarge Umiam Mining operated a limestone mine at Nongtrai in Meghalaya.
- The limestone was transported by conveyor belt to a cement plant in Bangladesh as part of a cross-border project.
- Initial documents and certificates described the mining land as:
- barren;
- rocky;
- outside notified forest.
- Environmental clearance was granted in 2001.
- Later inspections found natural vegetation and trees in parts of the mining lease.
- Questions arose as to whether the land was forest within the broad meaning adopted in Godavarman.
- Mining was stopped, and Lafarge applied for forest clearance under the Forest (Conservation) Act.
- The Ministry eventually granted environmental and forest clearances subject to extensive conditions.
- The Shella Action Committee challenged the process, alleging:
- concealment;
- inaccurate description of the land;
- violation of forest law;
- inadequate consideration of local and ecological interests.
Issue
- Whether Lafarge had obtained its earlier clearances through material suppression or misrepresentation.
- Whether the later forest clearance was valid.
- What standard courts should apply when reviewing expert environmental decisions.
- How local development, forests and tribal-community interests should be balanced.
Rule
- Diversion of forest land requires prior Central Government approval under Section 2 of the Forest (Conservation) Act.
- Environmental decision-making must observe:
- sustainable development;
- intergenerational equity;
- proportionality;
- transparency;
- consideration of local communities.
- Courts review whether the decision-making process was:
- informed;
- bona fide;
- based on relevant material;
- free from arbitrariness.
- Courts do not ordinarily substitute their own technical assessment for that of properly constituted expert bodies.
Application
- The Court examined the entire clearance history rather than focusing on one disputed description.
- Early government and autonomous-council certificates had themselves stated that the land was not forest.
- Lafarge had relied upon those official representations when seeking environmental approval.
- Once the forest issue was formally raised, mining was stopped and a full Forest (Conservation) Act process followed.
- The later appraisal included:
- Forest Advisory Committee consideration;
- site inspections;
- biodiversity studies;
- catchment treatment;
- compensatory afforestation;
- net present value;
- reclamation plans;
- interaction with local institutions.
- The Court found no sufficient basis to conclude that the final clearance was the product of deliberate fraud.
- It also examined the position of local Khasi institutions.
- The Nongtrai Village Durbar had supported the project and received:
- rent;
- employment;
- health facilities;
- schools;
- development benefits.
- Community support did not eliminate the need for environmental compliance, but it was a relevant social factor.
- The Court applied proportionality.
- Mining caused forest and biodiversity impacts, but the expert bodies had imposed measures intended to:
- minimise damage;
- restore mined land;
- protect water and catchment systems;
- compensate for forest diversion.
- The key question was therefore whether the statutory process had seriously evaluated the costs and safeguards.
- The Court concluded that it had.
Conclusion
- The Supreme Court upheld the forest clearance dated 22 April 2010 and permitted mining to resume subject to strict compliance with all conditions.
- Lafarge had to implement:
- compensatory afforestation;
- biodiversity management;
- catchment-area treatment;
- reclamation;
- community-development obligations;
- continuing monitoring.
- The Court emphasised transparent, accountable and expert environmental governance.
- It also directed the establishment of an independent national environmental regulator under Section 3(3) of the Environment Protection Act for appraisal and monitoring functions.
- The case is not authority for routine post-facto forest clearance.
- It upheld the project because of its particular history and the later detailed appraisal.
- Use this case for: judicial review of expert forest-clearance decisions and institutionalised sustainable development.