Environmental Law
M.K. Ranjitsinh v. Union of India - Great Indian Bustard Case III
2025 INSC 1472
- Citation
- 2025 INSC 1472
- Court
- Supreme Court of India
- Date
- 19 Dec 2025
- Bench
- P.S. Narasimha & Atul S. Chandurkar, JJ.
Facts
- Following the 2024 judgment, the Supreme Court-appointed expert committee studied:
- Great Indian Bustard habitat;
- bird movement;
- transmission lines;
- wind and solar infrastructure;
- undergrounding feasibility;
- conservation requirements.
- The committee identified revised priority areas in Rajasthan and Gujarat.
- It recommended differentiated measures rather than a single rule for every project.
- The Court considered objections from:
- conservationists;
- the Union Government;
- State authorities;
- renewable-energy developers;
- transmission agencies.
- The principal task was to convert the 2024 balancing exercise into a final and enforceable operational regime.
Issue
- What geographical areas required the highest level of protection.
- Which new energy projects and transmission lines should be prohibited or restricted.
- How existing infrastructure should be treated.
- Whether project-specific mitigation should replace blanket undergrounding.
Rule
- The survival of a critically endangered species requires landscape-level protection, not merely protection of individual birds.
- The precautionary principle permits strong restrictions where future development may cause irreversible habitat loss.
- Sustainable development requires scientifically differentiated regulation rather than either:
- unrestricted construction; or
- technically impossible universal prohibition.
- Expert recommendations should receive substantial weight where they result from multidisciplinary study and transparent evaluation.
- Existing projects do not obtain immunity from necessary mitigation merely because investment has already occurred.
Application
- The Court accepted that the Great Indian Bustard required clearly protected priority landscapes.
- It relied upon the expert committee’s field-based identification rather than retaining earlier boundaries without scientific revision.
- Within the revised priority areas, the Court treated further fragmentation as a serious survival threat.
- Power lines were not the only concern.
- Wind turbines, solar parks, roads and associated infrastructure could:
- disturb breeding;
- fragment movement corridors;
- increase collision risks;
- reduce usable habitat.
- The Court therefore applied different controls to different activities.
- New overhead lines were heavily restricted and generally had to use approved corridors or mitigation.
- Lower-voltage local systems could be treated differently where appropriate safeguards were available.
- New wind turbines were prohibited in the revised priority area because of both collision and habitat concerns.
- New large solar developments and expansion of existing solar parks were also restricted.
- For existing lines, the Court avoided automatic closure of all infrastructure.
- It required project-specific examination of:
- undergrounding;
- rerouting;
- line marking;
- bird diverters;
- removal of dangerous segments;
- habitat restoration.
- This recognised that some existing systems served essential public functions but still had to reduce their ecological impact.
- The Court accepted the committee’s approach because it connected each measure with:
- actual habitat use;
- bird behaviour;
- engineering feasibility;
- conservation urgency.
- It also emphasised that energy companies and public authorities share responsibility for biodiversity protection.
- Environmental responsibility cannot be limited to carbon reduction while ignoring species extinction.
Conclusion
- The Supreme Court substantially accepted the expert committee’s recommendations and issued final binding directions.
- Revised priority areas were recognised in Rajasthan and Gujarat.
- Within those areas:
- new overhead transmission was substantially restricted;
- dedicated routing and mitigation were required;
- new wind turbines were prohibited;
- new large solar projects and expansion of existing solar parks were restricted.
- Existing high-risk infrastructure had to undergo project-specific mitigation, including undergrounding, rerouting or bird-protection measures where recommended.
- The Court replaced the broad 2021 formula with a detailed, expert-led and landscape-specific regime.
- This 2025 judgment represents the current final stage of the three Great Indian Bustard decisions in the index.
- It demonstrates that renewable energy must itself be planned in an ecologically responsible manner.
- Use this case for: the final location-specific framework governing energy infrastructure in Great Indian Bustard habitat.