Judgement Briefs

Environmental Law

M.P. Patil v. Union of India

Appeal No. 12 of 2012; judgment dated 13 Mar 2014

Citation
Appeal No. 12 of 2012; judgment dated 13 Mar 2014
Court
National Green Tribunal, Principal Bench
Date
13 Mar 2014
Bench
Swatanter Kumar (Chairperson); U.D. Salvi (Judicial Member); G.K. Pandey, A.R. Yousuf & R.C. Trivedi (Expert Members)

Facts

  • NTPC proposed the 3 × 800 MW Kudgi Super Thermal Power Project in Karnataka.
  • The Ministry granted environmental clearance on 25 January 2012.
  • The appellant alleged that:
  • fertile irrigated land was incorrectly described as barren or dry;
  • public-hearing concerns were not properly answered;
  • the rehabilitation and resettlement plan was incomplete;
  • ambient-air monitoring locations were unsuitable;
  • coal sources had changed;
  • alternative sites and cumulative effects were inadequately examined.
  • The project involved major land acquisition and significant public investment.
  • By the time of adjudication, NTPC had acquired land and incurred substantial expenditure.

Issue

  • Whether material deficiencies in the EIA and appraisal process required cancellation of the environmental clearance.
  • Whether the EAC had adequately considered public-hearing concerns and rehabilitation.
  • Whether the project could be permitted through additional conditions under sustainable development.

Rule

  • Environmental decisions may be reviewed where authorities:
  • consider irrelevant material;
  • ignore material considerations;
  • act arbitrarily;
  • fail to comply with the Terms of Reference.
  • Sustainable development requires a balance between economic development and ecological protection.
  • Precautionary and polluter-pays principles apply under Section 20 of the NGT Act.
  • Public consultation must provide the EAC with the actual concerns and ground realities faced by affected persons.
  • Rehabilitation is an important component where environmental approval leads to large-scale livelihood displacement.

Application

  • The Tribunal found genuine defects in the appraisal.
  • A comprehensive R&R plan had not been available during the public hearing.
  • This deprived affected persons of the opportunity to evaluate:
  • compensation;
  • livelihood restoration;
  • employment;
  • treatment of landless workers;
  • consequences of losing agricultural land.
  • The public raised concerns about air pollution, ash, groundwater, crops, water withdrawal and peacock populations.
  • The EAC recorded these issues but did not fully resolve every deficiency.
  • However, the Tribunal did not consider cancellation the only lawful remedy.
  • NTPC was a public-sector undertaking and large amounts of public money had already been committed.
  • Electricity generation was also relevant to regional development.
  • The Tribunal applied a balancing approach:
  • irreversible environmental harm could not be allowed;
  • public investment need not be wasted if strict conditions could control the impact.
  • It therefore treated sustainable development as conditional permission—not unconditional project approval.
  • NTPC had to implement enhanced pollution control, rehabilitation and monitoring measures.
  • The project’s environmental load had to remain within prescribed limits.
  • Livelihood loss had to be addressed through an effective R&R scheme rather than merely monetary land acquisition.

Conclusion

  • The NGT did not cancel the environmental clearance.
  • It sustained the project subject to strengthened conditions concerning:
  • comprehensive rehabilitation and resettlement;
  • employment and livelihood measures;
  • strict pollution-control compliance;
  • environmental monitoring;
  • protection of affected communities.
  • The judgment recognised defects in the original process but concluded that they could be addressed without abandoning the entire public project.
  • It is an example of remedial environmental adjudication through conditions and monitoring.
  • Use this case for: conditional preservation of an environmental clearance despite deficiencies, where strict corrective measures can secure sustainable development.