Environmental Law
Narmada Bachao Andolan v. Union of India
(2000) 10 SCC 664
- Citation
- (2000) 10 SCC 664
- Court
- Supreme Court of India
- Date
- 18 Oct 2000
- Bench
- A.S. Anand, CJI; S.P. Bharucha & B.N. Kirpal, JJ.
Facts
- The Sardar Sarovar Dam was constructed across the River Narmada as an inter-State project involving Gujarat, Madhya Pradesh, Maharashtra and Rajasthan.
- Its proposed benefits included:
- irrigation;
- drinking-water supply;
- electricity generation;
- drought relief.
- The project also involved:
- submergence of villages and forests;
- displacement of tribal and rural communities;
- loss of agricultural land;
- impacts upon river ecology.
- Narmada Bachao Andolan challenged further construction of the dam.
- It argued that:
- the environmental clearance granted in 1987 was conditional and incomplete;
- necessary environmental studies were not completed before approval;
- rehabilitation had not progressed alongside construction;
- increasing the dam height would cause irreversible harm.
- The Union and State Governments argued that the project had undergone prolonged expert examination and that further work was necessary to secure major public benefits.
Issue
- Whether the environmental clearance granted to the project was legally valid.
- Whether construction could proceed while environmental studies and rehabilitation measures remained incomplete.
- How the Court should balance development benefits against ecological harm and displacement.
Rule
- Sustainable development permits economic development, but requires environmental safeguards to be integrated into the project.
- The precautionary principle is especially important where the environmental consequences are uncertain or insufficiently studied.
- Courts reviewing technical projects examine whether:
- the competent authorities considered relevant material;
- statutory requirements were followed;
- the decision was arbitrary or mala fide.
- Environmental protection and rehabilitation must progress pari passu, meaning at the same pace, with dam construction.
Application
- The majority distinguished between:
- a project whose effects were unknown; and
- a project whose impacts had been studied and for which mitigation measures had been prescribed.
- It found that the Sardar Sarovar Project had been examined for many years by:
- expert committees;
- the Narmada Water Disputes Tribunal;
- State and Central authorities;
- environmental sub-groups.
- The 1987 environmental clearance was conditional, but the majority did not treat this as making it invalid.
- It viewed the conditions as permitting continuing studies while construction proceeded in controlled stages.
- The Court stressed that environmental concerns could not be separated from rehabilitation.
- Before increasing the dam height, authorities had to ensure that families affected at that level received:
- alternative agricultural land;
- housing sites;
- civic facilities;
- resettlement in accordance with the Tribunal Award.
- Construction was therefore not given an unrestricted approval.
- Each further increase in height required clearance by the designated environmental and rehabilitation bodies.
- The majority also considered the project’s social benefits.
- It found that irrigation and drinking water for drought-prone regions were relevant components of sustainable development.
- The Court stated that policy choices involving complex engineering and resource allocation should not ordinarily be replaced by judicial preference where the decision-making process was lawful.
- Justice Bharucha dissented.
- He considered the environmental clearance legally deficient because necessary studies had not been completed before approval.
- In his view, construction should not proceed until a comprehensive environmental appraisal was completed.
Conclusion
- By majority, the Supreme Court allowed construction to continue in stages.
- Every increase in dam height was made subject to prior confirmation that:
- environmental safeguards had been implemented;
- rehabilitation had progressed pari passu;
- affected families had received lawful resettlement.
- The grievance-redressal authorities were required to monitor rehabilitation.
- The judgment did not hold that development automatically prevails over the environment.
- It upheld the project because the majority believed that an institutional system existed for staged environmental and rehabilitation compliance.
- Use this case for: judicial review of large development projects and the requirement that environmental protection and rehabilitation proceed alongside construction.