Environmental Law
Praffula Samantra & Anr. v. Union of India & Ors. - POSCO Case
Appeal No. 8 of 2011
- Citation
- Appeal No. 8 of 2011
- Court
- National Green Tribunal, Principal Bench
- Date
- 30 Mar 2012
- Bench
- C.V. Ramulu (Judicial Member) & R. Nagendran (Expert Member)
Facts
- POSCO proposed an integrated steel plant, captive power plant and port in Odisha.
- Separate environmental clearances were granted in 2007 for different components of the project.
- The proposal was presented in phases, beginning with approximately 4 million tonnes per annum, although the ultimate capacity was planned at approximately 12 million tonnes.
- Serious concerns arose regarding:
- cumulative pollution;
- water demand;
- coastal impact;
- port development;
- forest diversion;
- effect on local communities.
- The Ministry appointed review committees.
- A majority report expressed substantial concerns, while a minority report by Meena Gupta favoured continuation with additional safeguards.
- On 31 January 2011, the Ministry allowed the clearances to continue subject to further conditions.
- Environmental activists challenged that decision before the National Green Tribunal.
Issue
- Whether the Ministry had conducted an adequate and independent environmental review.
- Whether the cumulative impact of the complete 12 MTPA project had been assessed.
- Whether reliance upon assurances and a minority report satisfied environmental appraisal requirements.
- What relief the Tribunal could grant despite limitation affecting the original 2007 clearances.
Rule
- Environmental appraisal must be:
- reasoned;
- scientifically informed;
- independent;
- based on the project’s real cumulative impact.
- A project cannot be artificially divided into components or phases to avoid full assessment.
- Expert Appraisal Committees must apply their own mind and cannot merely accept the project proponent’s assurances.
- Sustainable development and the precautionary principle require investigation before irreversible construction begins.
- An appellate tribunal may suspend a later review order where that order rests upon inadequate appraisal.
Application
- The Tribunal distinguished between:
- direct challenges to the original 2007 clearances, which faced limitation difficulties; and
- the Ministry’s fresh order dated 31 January 2011, which was properly before it.
- It examined whether the later Ministry review had genuinely cured the earlier deficiencies.
- The Tribunal found that the project’s environmental footprint could not be judged only by reference to the first 4 MTPA phase.
- Land, infrastructure, water supply, port capacity and pollution implications were connected with the ultimate 12 MTPA project.
- A fragmented appraisal risked understating:
- emissions;
- water consumption;
- waste;
- displacement;
- coastal impact;
- cumulative industrial pressure.
- The Ministry had substantially relied upon the minority committee report without adequately explaining why the majority’s concerns were rejected.
- The Tribunal also criticised reliance on future promises that detailed studies would be completed after approval.
- Environmental clearance is meant to evaluate risk before the project creates irreversible commitments.
- It cannot be reduced to conditional acceptance followed by later investigation.
- The Tribunal required fresh examination by properly constituted specialist bodies with expertise relevant to:
- steel;
- power;
- ports;
- coastal ecology;
- cumulative environmental impact.
Conclusion
- The NGT suspended the Ministry’s order dated 31 January 2011.
- It directed a fresh environmental review by properly constituted expert bodies.
- The review had to assess:
- the integrated and ultimate project capacity;
- cumulative impacts;
- carrying capacity;
- water requirements;
- pollution;
- port and coastal effects;
- community concerns.
- The Ministry was required to take a fresh final decision after the expert appraisal.
- The Tribunal did not permanently prohibit the POSCO project.
- It held that such a large integrated project could not proceed on an incomplete, fragmented or unreasoned environmental assessment.
- The case is an important NGT authority on substantive EIA review and cumulative-impact appraisal.
- Use this case for: suspension of environmental approval where a mega-project’s cumulative and ultimate impact was not properly assessed.