Judgement Briefs

Environmental Law

Praffula Samantra & Anr. v. Union of India & Ors. - POSCO Case

Appeal No. 8 of 2011

Citation
Appeal No. 8 of 2011
Court
National Green Tribunal, Principal Bench
Date
30 Mar 2012
Bench
C.V. Ramulu (Judicial Member) & R. Nagendran (Expert Member)

Facts

  • POSCO proposed an integrated steel plant, captive power plant and port in Odisha.
  • Separate environmental clearances were granted in 2007 for different components of the project.
  • The proposal was presented in phases, beginning with approximately 4 million tonnes per annum, although the ultimate capacity was planned at approximately 12 million tonnes.
  • Serious concerns arose regarding:
  • cumulative pollution;
  • water demand;
  • coastal impact;
  • port development;
  • forest diversion;
  • effect on local communities.
  • The Ministry appointed review committees.
  • A majority report expressed substantial concerns, while a minority report by Meena Gupta favoured continuation with additional safeguards.
  • On 31 January 2011, the Ministry allowed the clearances to continue subject to further conditions.
  • Environmental activists challenged that decision before the National Green Tribunal.

Issue

  • Whether the Ministry had conducted an adequate and independent environmental review.
  • Whether the cumulative impact of the complete 12 MTPA project had been assessed.
  • Whether reliance upon assurances and a minority report satisfied environmental appraisal requirements.
  • What relief the Tribunal could grant despite limitation affecting the original 2007 clearances.

Rule

  • Environmental appraisal must be:
  • reasoned;
  • scientifically informed;
  • independent;
  • based on the project’s real cumulative impact.
  • A project cannot be artificially divided into components or phases to avoid full assessment.
  • Expert Appraisal Committees must apply their own mind and cannot merely accept the project proponent’s assurances.
  • Sustainable development and the precautionary principle require investigation before irreversible construction begins.
  • An appellate tribunal may suspend a later review order where that order rests upon inadequate appraisal.

Application

  • The Tribunal distinguished between:
  • direct challenges to the original 2007 clearances, which faced limitation difficulties; and
  • the Ministry’s fresh order dated 31 January 2011, which was properly before it.
  • It examined whether the later Ministry review had genuinely cured the earlier deficiencies.
  • The Tribunal found that the project’s environmental footprint could not be judged only by reference to the first 4 MTPA phase.
  • Land, infrastructure, water supply, port capacity and pollution implications were connected with the ultimate 12 MTPA project.
  • A fragmented appraisal risked understating:
  • emissions;
  • water consumption;
  • waste;
  • displacement;
  • coastal impact;
  • cumulative industrial pressure.
  • The Ministry had substantially relied upon the minority committee report without adequately explaining why the majority’s concerns were rejected.
  • The Tribunal also criticised reliance on future promises that detailed studies would be completed after approval.
  • Environmental clearance is meant to evaluate risk before the project creates irreversible commitments.
  • It cannot be reduced to conditional acceptance followed by later investigation.
  • The Tribunal required fresh examination by properly constituted specialist bodies with expertise relevant to:
  • steel;
  • power;
  • ports;
  • coastal ecology;
  • cumulative environmental impact.

Conclusion

  • The NGT suspended the Ministry’s order dated 31 January 2011.
  • It directed a fresh environmental review by properly constituted expert bodies.
  • The review had to assess:
  • the integrated and ultimate project capacity;
  • cumulative impacts;
  • carrying capacity;
  • water requirements;
  • pollution;
  • port and coastal effects;
  • community concerns.
  • The Ministry was required to take a fresh final decision after the expert appraisal.
  • The Tribunal did not permanently prohibit the POSCO project.
  • It held that such a large integrated project could not proceed on an incomplete, fragmented or unreasoned environmental assessment.
  • The case is an important NGT authority on substantive EIA review and cumulative-impact appraisal.
  • Use this case for: suspension of environmental approval where a mega-project’s cumulative and ultimate impact was not properly assessed.